Electrolyzer Installation at the Agios Dimitrios PPC Power Plant

On April 30, 2024, the electrolyzer (part of the pilot unit) has been installed at the premises of Agios Dimitrios PPC Power Plant! The electrolyzer as part of the mobile hybrid energy storage system of the LIFE CO2toCH4 project, will be used to produce pure hydrogen (H2), through electrolysis of water, which will then be fed to the methanation unit.

The entire process was supervised by the project coordinator Dr. Apostolos Antoniadis (PPCR), Prof. Anastasios Zouboulis (AUTh), Dr. Froso Peleka (AUTh), Alexandros Chatzis (AUTh), Emmanouil Sakalis (PPC), Evaggelos Papazisis (PPC) and Helen Partheniou (PPCR).

The rest of the equipment is anticipated to be installed within the next months!